Operations, as Taught by Eli Goldratt · Lesson 2 of 8
Tell me how you measure me
Follow one measurement, tons per hour, through a steel mill and watch it produce every undesirable effect on Daniel's whiteboard. Goldratt's current reality tree, built step by step, and why V-plants suffer most from “stealing”.
Ruth Adler, the TOC coach Daniel has invited, walks the mill with him. Above the hot-rolling mill hangs a big electronic board: 512 tonnes/hour.
Ruth: “Who looks at that number?”
Daniel: “Everyone. Viktor, who runs the rolling mill, gets his bonus on it. If he meets his tons per hour, nobody asks him anything else. If he misses it, nothing else he did matters.”
Ruth: “Then let’s see what that number does to your whiteboard.”
The mode of managing is expressed in its measurements
How an operation is managed shows up in what it measures, and the measurement controls behaviour. In almost every operation there is a local efficiency measurement. In steel it is tons per hour; elsewhere it is units per shift, utilisation, earned hours or cost per piece. For decades tons per hour was the prime measurement in steel: meet it and you can get away with anything; miss it and nothing else counts.
“Tell me how you measure me, and I will tell you how I will behave.” — Eliyahu M. Goldratt
So let’s follow tons per hour, step by step, the way Goldratt did.
Step by step through the tree
The start. Tons per hour is the prime measurement, and most people behave in line with the way they are measured. So every department tries to maximise its tons per hour.
Branch 1: fast items first. In most departments some items take less time per tonne than others. A thick plate rolls more tonnes per hour than a thin one.
Viktor has orders for 2-inch plate and 1-inch plate, and a month-end tons-per-hour target. What will he roll first?
- Whatever is due first
- The thick plate: more tonnes per hour
- Whatever the planner says, in due-date order
To look good in the measurement period, departments roll the fast items at the expense of the slow ones. The slow items, whatever their due dates, wait. Result: poor due-date performance and too many customer complaints.
Branch 2: produce for stock. Not producing at all scores zero tons per hour. So when there are no orders, departments produce anyway, for stock, even with no market request in the short or medium term. Result: inventories too high and, with money tied up in steel nobody ordered, payback periods too long.
Branch 3: bigger batches. Every set-up, changing the alignment of the rolls, means hours without producing, which lowers tons per hour. So departments pull orders forward from future weeks to make each batch bigger. Result: work that isn’t needed yet is done now, and work that is needed waits behind it: long lead times, high inventory, poor due-date performance.
Branch 4: stealing. Steel is a V-plant: from one slab come hundreds of end items, differing in width, thickness, surface and grade. Every step is a divergence point where material can go to more than one order. To feed a big efficient batch, a department takes material intended for one order and uses it for another, which then has to be made again from scratch. Goldratt called it stealing. It feeds every UDE on the board, including the last one: when one department keeps taking another’s material, relationships between departments go bad.
Go over the tree again, arrow by arrow, and check one thing: as long as local efficiency is the prime measurement, the undesirable effects are bound to exist. No planning system, reorganisation, merger or psychologist removes them, because none of them touches the cause.
Exercise: which behaviour driven by local efficiency is this?
- The cutting line uses plate reserved for an urgent export order, because it completes a full batch of another size.
- The furnace keeps running at the weekend to make slabs “we’ll surely need”.
- The mill rolls next month’s orders of the same grade now, to avoid a roll change.
- The thin-gauge order slips again; the thick plates are always rolled first.
Four types of plant
Goldratt classified operations by the shape of their flow, because each shape produces its own typical UDEs:
- V-plants: few raw materials, many end products, many divergence points (steel, textiles, paper, chemicals). Typical damage: stealing.
- A-plants: many parts converging into few products (machinery, aircraft). Typical damage: parts waiting at assembly for the one that’s missing.
- T-plants: a limited set of parts combined at the end into many variants (appliances, electronics). Typical damage: stealing at final assembly.
- I-plants: a straight line, one route.
The details differ, but the root is the same in all four: efficiency used as the prime measurement.
But there must be a good reason
If one measurement does so much damage, why is it the prime measurement almost everywhere? Goldratt insisted that defining the core problem needs one more step: understanding why the system goes along with the problematic measurement. There must be a good reason. That is the next lesson.
Check your understanding
Answer all five. Get four right to complete the lesson.
1. Why does tons per hour lead to poor due-date performance?
- Workers are lazy
- The machines are old
- Fast items are rolled at the expense of slow ones, whatever their due dates
- Customers order late and change their orders after they are confirmed
The measurement rewards what is fast, not what is due.
2. Producing for stock with no orders happens because…
- Not producing scores zero on the efficiency measurement
- The forecast says the products will be needed soon anyway
- Stock is cheap
- Customers prefer it
Idle time looks like failure under a local efficiency measurement.
3. “Stealing” is typical of which plant type?
- I-plant
- A-plant
- None
- V-plant, with its many divergence points
And of final assembly in T-plants.
4. The tree shows that, as long as local efficiency is the prime measurement…
- The UDEs can be fixed one by one
- The UDEs are bound to exist
- Inventory will fall
- Only V-plants suffer
The measurement is the common cause.
5. Before declaring the core problem, TOC also asks…
- Who introduced the measurement, and when it was last reviewed
- How much it costs
- Why the system continues to comply with it
- What competitors measure
There must be a good reason, and it will turn out to be a conflict.