EPC contractors: from firefighting to flow

When the economy slows, engineering, procurement and construction (EPC) companies feel it quickly. Advances from new projects dry up, collections from running projects slow down, borrowing rises and interest eats into profits. It looks like a macroeconomic problem, beyond any single company’s control.
But look at how EPC companies actually perform, and a pattern appears. Margin losses and working capital problems are closely tied to something each company does control: how long its projects take to execute. When sites take far longer than planned to close, money leaks out through site expenses and missing material, and the last tranche of payment, tied to handover, is delayed.
The health check: openings vs closures
One simple way to judge an EPC company’s health is to compare two curves over time: the cumulative number (or value) of projects won, and the cumulative number closed.
- The stable zone. Closures keep pace with new orders. Receivables are under control. The company can grow steadily.
- The unstable zone. Closures slow down. Many sites stay open. Customers complain of delays. Cash gets tight and receivables rise.
- The crisis zone. New projects keep coming in, but old ones never close. Receivables and borrowings spiral. The board pushes management to stop taking new work and close old sites. Write-offs follow.
A company in the crisis zone can still show turnover growth for a while. Meanwhile, execution margins collapse and cash disappears. Smaller EPC companies can be wiped out in this phase.
The health of an EPC company shows less in its turnover than in its rate of closing projects.
The arithmetic is unforgiving. Suppose a company wins 40 projects a year but closes only 30. Every year, ten more sites stay open. If it carries 60 open projects and closes 30 a year, the average project is taking two years from award to closure, whatever the contracts say. Each open site carries a site office, a few people, unbilled work and retention money. Cut the average closure time to a year with the same order intake, and the number of open sites halves, along with much of the working capital they hold.
The biggest waste: managing by turnover
Most EPC companies are driven by turnover targets for each month and quarter. When different items in a project carry different billing values, design and procurement focus on high-value items, whether or not the site needs them now. Sites end up with plenty of material for later, while they wait for the small parts needed to finish today’s work.
Near handover, there are many issues to resolve and the project needs a lot of management attention. But by then most of its turnover is already booked. A turnover-focused company turns its attention to billing other projects. The last part of the receivables (often the entire profit on the project) piles up. Years later, when the company tries to close those sites, write-offs become the only way out.
Interruptions are the enemy
Experienced EPC managers know that work goes fastest when it isn’t interrupted. The main sources of interruption are:
- Priority conflicts between projects and departments.
- Flow-backs: work returned from downstream for corrections.
- Waiting for information, approvals or vendor inputs.
Design teams switch between modules and projects constantly. They release drawings based on assumptions, which come back for corrections. Purchasing and design argue about priorities. Customers’ pending inputs add delay. Sites missing drawings or material run with thin crews and open multiple work fronts to keep labour busy, so every site moves slowly.
The usual response, after the fact, is to plan in more detail. But with thousands of unique items and drawings, many projects and shared resources, detailed item-level plans go out of date within weeks.
Three flow rules
Rule 1: Gate the work and limit work in progress. Limit how many independent design modules are open at once. A new module starts only when an active one meets its closure criteria. Use those same criteria as a no-start gate for the next phase, including site work. This aligns design with purchasing: equipment is specified and ordered on time, vendor inputs arrive while engineering can still use them, and flow-backs drop. Modules waiting in the queue give time to collect missing information from customers.
Rule 2: One stable priority system for everyone. With work in progress under control, most tasks run close to their actual working time. Plan them that way, and pool the safety into a shared project buffer. Use buffer consumption against progress as the common priority signal for every department. Align equipment manufacturing with the site erection sequence, not with the manufacturer’s billing convenience, so parts arrive in the order they are needed.
Rule 3: A fixed rhythm of review. Since tasks are planned tightly, a missed task isn’t a personal failure, but it can’t be ignored until a deadline either. Supervisors review active tasks daily, to maximise working time and clear obstacles. Senior managers review weekly or fortnightly, focusing on their critical areas. Problems are caught early, by routine.
EPC companies that adopt these rules typically see execution lead times fall, more sites closed per year, new projects running ahead of schedule, and working capital falling sharply. Getting there may first mean biting the bullet on old, chronic projects. But a company in the stable zone grows on its own cash.