Every team leader gets work done through others. On paper, that seems easy: leaders have authority and can simply assign tasks.
Ask team leaders how it actually goes, though, and you hear the same frustration in every kind of organisation: “Despite reminders, things just don’t get done on time.”
What leaders usually try
Asking for a commitment date. “When will you finish?” People commit, then many miss. Leaders conclude that people commit to unrealistic dates, or lack motivation.
Standard times. Experts set “standard” durations for common tasks, and people are held to them.
Rewards and penalties linked to actual versus planned completion. Popular, but research and experience both show its limits, and it can backfire.
Tracking tools and more reviews. Problems seem to reach management only at the last moment. Leaders suspect people hide problems, so they buy software for “real-time visibility” or hold longer, more frequent review meetings.
Each of these helps a little. None changes the basic pattern: work still finishes late.
Why these tactics fall short
Task times are uncertain. Think of cooking a familiar dish for dinner. You have made it a hundred times. You still can’t say exactly how long it will take tonight: maybe 30 minutes, maybe 45, depending on whether an ingredient is missing, the gas cylinder runs out, or the phone keeps ringing. Most work is like this. No amount of skill or motivation removes uncertainty that comes from outside the task.
Commitments make people defensive. Asked for a date in an uncertain world, a person faces a choice: give a short, optimistic date and risk missing it, or give a padded, safe date. If rewards and penalties hang on the answer, the safe date wins.
Safety time gets used up anyway. Knowing there is slack, people start late (student syndrome), or let work expand to fill the time (Parkinson’s law). Neither software nor reviews stop this; both can be gamed. And people learn not to finish early, in case their next estimate is cut.
Leaders then conclude the problem is people’s capability or attitude. Usually, it isn’t.
Where the time really goes
Any task’s duration has two parts:
Task time = actual working time + waiting time
The working time varies with uncertainty, and we can’t control that. But much of the waiting is within the team’s control. The three biggest causes:
- Multitasking: a task is started, then dropped when something else seems more urgent, and left waiting.
- Missing inputs: work started with partial information, then stopped until the rest arrives.
- Unexpected obstacles that sit unresolved for days.
Remove these, and a task is done about as fast as it can be, whatever the circumstances.
Three simple rules
1. Stop multitasking.
- Everyone lists all their pending tasks and ranks them by priority.
- Put the most people possible on the top task; if anyone is left over, the next; and so on.
- Tasks being worked on are active; everything else waits on a waiting list, with no work on it.
- When an active task meets its completion criteria (finished well enough for the next person to use), the top waiting task becomes active: one out, one in.
- No one, including the most senior person in the company, interrupts an active task to start another.
2. Start with a full kit.
- A full kit is everything needed to finish the task, not just to start it.
- While tasks wait, the team leader gathers their full kit, in priority order.
- A waiting task becomes active only when its full kit is ready, even if it is next in line.
3. Hold a daily flow meeting.
- Same time, same place, same people, every day, for a few minutes.
- Review what moved in the last 24 hours and what each person expects to complete in the next 24.
- If progress has stalled, there is an obstacle, and the meeting gets it resolved quickly.
Here is what two minutes of a daily flow meeting can look like in a team of six:
- Anil: “Pump layout: I expected to finish the piping today, but I’m still waiting for the nozzle loads from Priya’s team.” Obstacle. The team leader calls Priya’s lead after the meeting.
- Meena: “Cost estimate: about two days left, same as yesterday’s estimate minus one.” Moving. No discussion needed.
- Ravi: “Panel drawing: done, completion criteria met.” One out. The next task on the waiting list, whose full kit is ready, becomes active today.
No dates were negotiated and nobody was chased. One stuck task was found within a day instead of at the next weekly review, and freed within hours.
Teams that follow these rules in letter and spirit typically see tasks completed significantly faster, and often far more output from the same people, without adding staff and without taking much of senior management’s time.
Chasing people for dates makes them protect themselves. Removing what makes them wait makes them fast.