Every country that wants to grow needs roads, ports, power and water systems built quickly. Yet many infrastructure companies are weighed down by debt, and much of that debt doesn’t fund new assets. It funds working capital: money tied up in receivables and inventory. Even well-run companies in this sector often use a large share of their borrowing just to keep projects moving. When liquidity tightens, banks become unwilling to lend more, and stalled projects pile up.
On the surface, this looks like a problem of slow-paying clients and a tough economy. Look closer, and part of it turns out to be self-inflicted.
The pattern in the numbers
Track an infrastructure company’s turnover and working capital through the year, and two patterns stand out:
- Turnover spikes at the end of every quarter, and spikes even higher at the end of the financial year.
- Working capital follows the spikes. After each spike, receivables balloon. The worst point is often the first quarter of the new year.
Why? Because revenue booked in a rush doesn’t bring cash in a rush. Billing to clients gets batched; a single error or missing document can hold up a whole batch of invoices. And at quarter end, the focus is on booking turnover internally, not on clean, timely billing to the client.
Put numbers to it. A company with ₹12,000 million of annual turnover books about ₹3,000 million a quarter, but around ₹1,500 million of it in the last month. If clients take 60 days to pay clean invoices, and a fifth of the quarter-end invoices are held up for corrections for another two months, the company is carrying hundreds of millions more in receivables than its contracts require, every quarter, at the interest rate of its short-term loans.
The turnover bias
The spikes come from a turnover bias: shaping material flow and execution to hit quarter-end and year-end numbers.
In material-heavy projects, managers supply high-value items to sites to book sales. To find enough of them, they open many work fronts at once. But the complete set of material needed to finish any one stretch of work arrives only in fits and starts. Crews move back and forth to complete each stretch, wasting time and capacity. Site costs rise; projects slip.
In erection-heavy projects, contractors pick the most billable jobs first, opening many fronts to harvest them. Without enough supervisors to finish them all, the project drags.
Clients have noticed. Many now link more of the payment to erection and completion. Yet many contractors keep cherry-picking. After a big year-end, there is little left to cherry-pick in the first quarter, sales dip, and the pressure to cherry-pick returns.
When the downturn arrives
In a recession, the pattern turns into a crisis. New projects dry up, and with them the advances that were quietly funding older projects. Many open projects are near their tail end, where there is little turnover left to book and nothing left to cherry-pick. To meet working capital needs, companies take expensive short-term loans. Delayed projects bring angry clients, penalties, cost overruns and write-offs. Thin margins disappear, and debt grows.
Breaking the loop: from turnover focus to closure focus
The way out is to manage for rapid execution and closure, and let turnover follow. Four rules help:
- Pull material to the pace of execution. Move material to site according to how fast work is actually progressing, not to book sales.
- Buy complete kits, not high-value items. Remove value targets in purchasing. Measure purchasing on supplying the full set of material needed to complete each stretch of work.
- Limit open sites. Within each project, open only as many work fronts as there are supervisors to run them properly. Open a new one only when an active one is closed.
- Manage daily. Resolve every issue that blocks flow as soon as it appears.
These rules keep management attention on closing work. Lead times fall. Faster completion raises the rate of turnover naturally, so there is no need to manipulate material or billing at quarter end. Project by project, delivery dates are met, the quarterly skew fades, and working capital comes down and becomes far more predictable.
Companies that make this shift often free up a large share of their working capital, money that can fund new projects instead of being trapped in old ones.
In infrastructure, booked turnover is not cash. Closed work is.